Network Rail extends working hours on Oxford station following delays

Credit: Network Rail

Work on the £161m Oxford station and railway upgrade was paused in June, after contractors unearthed an inverted brick arch under the road at Botley Road bridge.

Archaeologists believe the arch is part of a Victorian water system, designed to keep river water away from the railway and city.

A new work schedule has had to be drawn up to safely remove the brick arch before work to divert the utilities below Botley Road can continue.

Work was also paused on Thursday 20 July, when the area had to be evacuated following the discovery of a WWII era hand grenade within the work site, near to the railway tracks.

Officers from British Transport Police attended the incident, alongside personnel from Explosives Ordinance Disposal.

Starting on Saturday 2 September, work will be carried out on site 24/7. To reduce disturbance to those in the area, the nosiest work will be carried out during the day.

This revised approach has been agreed with Oxford City Council, in consultation with Oxfordshire County Council.

Work is now back underway on the multi-million-pound project to upgrade the station, the railway and the surrounding local road network that will boost passengers’ travel experience. Once complete, the station and railway upgrades - part of the Oxfordshire Connect programme – will provide travellers with a bigger and better Oxford station and an expanded railway which will enable more services for passengers and freight, with reduced journey times.

The road network near the station will also be improved, with safer junctions with Botley Road and more opportunities for sustainable transport, including enhanced bus travel as well as more space for cyclists and pedestrians through the addition of a four-metre cycle and footway on each side of the main road.  

 

Credit: Network Rail

Philip Morton, project manager at Network Rail said: "Whilst we knew the arch was there, it’s much larger than our original ground surveys identified, which has added a unique layer of complexity to our ongoing work to upgrade of Oxford station and surrounding areas.

“Due to its potential significance in supporting the bridge, removing the arch from beneath Botley Road is now our biggest challenge, but we’re addressing it as safely and efficiently as possible.

“Following further investigations, our new work plan involves installing piles to stabilise the bridge while we excavate the brickwork before we can continue to divert the utilities.

“Going forward, we will be working day and night so we can gain back some of the time lost, with the majority of the noisy work planned to take place during the day, to minimise disruption for the local community. As ever, we appreciate everyone’s patience while we manage this unexpected challenge.”

Mark Dodd of Oxford Archaeology said: "The historic city of Oxford contains archaeological remains dating back to the prehistoric period, so there's always the potential to discover a bit of history beneath the ground.

“Owing to the existing road, the site itself wasn’t an ideal location for archaeology, so the best approach was for us to be on site whilst the works are underway. It’s likely the arch was used to help manage the groundwater owing to its low-lying position close to the river Thames and this is an excellent example of a Victorian engineering solution, as seen elsewhere throughout Britain at this time."

                            

                          Credit: Network Rail